Die CPM Methode- Critcal Path Methode

Oracle Primavera implementiert im Kern die CPM Methode um den kritischen Pfad in einem Projekt zu finden.

Die wichtigsten Begriff in der Übersicht:

Float - Float or slack is the amount of time that a task in a project network can be delayed without causing a delay

Die Eigenschaften einer Aktivität in diesen Zusammenhang:
ES Early start It is the earliest time that an activity can start
EF Early finish It is the earliest time that an activity can finish
LS Late start It is the late time that an activity can start
LF Late finish It is the late time that an activity can finish
D Duration Duration Of activities
F Float The float for an activity is the amount that its duration can slip without causing the project to be delayed

Formel um diese Werte auf einer Aktivität bzw. der folgenden/vorherigen Aktivität zu berechnen:

ES Early start ES=Max(EF(activity before))+1
EF Early finish ES+Duratoin of this activity -1
LS Late start LS=LF-Duratoin+1
LF Late finish LF=Min(LS(activity after))-1
F Float F = LS-ES

Übersicht

Die Aktivitäten des Plans:

 The List of activities

Netzwerk als einfacher Vorgangspfeil-Netzplan

CPM - Critial Path

In Primavera PPM Desktop

In Primavera kann das dann als Gant oder Netzwerk dargestellt werden

CPM in Oracle Primavera PPM Desktop

Tipp:

„Free Float“ kann als kleiner schwarzer Balken dargestellt werden, im PPM Desktop auf den Button „Bars“ und die Anzeige der Float Bar aktivieren

 Free Float Anzeige als Balken im Gant Diagramm aktivieren - Oracle Primavera PPM Desktop

Quellen

Einführung

Float