=====Die CPM Methode- Critcal Path Methode ===== Oracle Primavera implementiert im Kern die CPM Methode um den kritischen Pfad in einem Projekt zu finden. Die wichtigsten Begriff in der Übersicht: **Float** - Float or slack is the amount of time that a task in a project network can be delayed without causing a delay * Free Float - the amount of time the selected activity can be delayed without delaying the activities that immediately follow * Total Float - amount of time the selected activity can be delayed without delaying the project's finish date ==Die Eigenschaften einer Aktivität in diesen Zusammenhang:== |**ES** | Early start |It is the earliest time that an activity can start | |**EF** | Early finish |It is the earliest time that an activity can finish | |**LS** |Late start | It is the late time that an activity can start | |**LF** | Late finish | It is the late time that an activity can finish | |**D** | Duration | Duration Of activities | |**F** | Float | The float for an activity is the amount that its duration can slip without causing the project to be delayed | Formel um diese Werte auf einer Aktivität bzw. der folgenden/vorherigen Aktivität zu berechnen: |**ES** | Early start | ES=Max(EF(activity before))+1 | |**EF** | Early finish | ES+Duratoin of this activity -1| |**LS** | Late start | LS=LF-Duratoin+1 | |**LF** | Late finish | LF=Min(LS(activity after))-1 | |**F** | Float | F = LS-ES | ===Übersicht=== Die Aktivitäten des Plans: {{ :prod:prima:cpm_critical_path_method_for_primavera_activities_v01.png?300 | The List of activities }} Netzwerk als einfacher Vorgangspfeil-Netzplan {{ :prod:prima:cpm_critical_path_method_for_primavera_v01.png?600 |CPM - Critial Path}} === In Primavera PPM Desktop === In Primavera kann das dann als Gant oder Netzwerk dargestellt werden {{ :prod:prima:cpm_critical_path_method_for_primavera_v02.png?600 |CPM in Oracle Primavera PPM Desktop }} **Tipp:** "Free Float" kann als kleiner schwarzer Balken dargestellt werden, im PPM Desktop auf den Button "Bars" und die Anzeige der Float Bar aktivieren {{ :prod:prima:cpm_critical_path_method_for_primavera_float_bar_v01.png?500 | Free Float Anzeige als Balken im Gant Diagramm aktivieren - Oracle Primavera PPM Desktop }} ==== Quellen ==== Einführung * http://web.stanford.edu/class/cee320/CEE320B/CPM.pdf * https://de.wikipedia.org/wiki/Methode_des_kritischen_Pfades Float * http://www.dau.mil/pubscats/ATL%20Docs/Jan_Feb_2012/Devaux.pdf